700 Tons/day MSW Incineration Power Plant, PhuketCustomer: PJT Technology Co., Ltd.
Period: May, 2012 – March, 2013
Details of Service: Consulting Service for proper fabrication and initial operations of the plant in order to prolong the life of the plant to be as long as possible. -
Wastewater Treatment Plant No. 1, AMATA CITY Industrial EstateCustomer: Amata Water Co., Ltd.
Period: December 2010 – Present
Details of Service: O&M for 13,500 m3/day-Central Wastewater Treatment No. 1 of AMATA CITY Industrial Estate including system improvement by the latest technology from Japan “Suzuki Aeration System” which can very much reduce electricity consumption while the quality of treated wastewater become even better. -
Wastewater Treatment Plant No. 2, AMATA NAKORN Industrial EstateCustomer: Amata Water Co., Ltd.
Period: September 2008 – Present
Details of Service: O&M for 12,000 m3/day-Central Wastewater Treatment No. 2 of AMATA NAKORN Industrial Estate including system improvement by the latest technology from Japan “Suzuki Aeration System” which can very much reduce electricity consumption while the quality of treated wastewater become even better. -
Bangpoo Industrial Waste Incineration PlantCustomer: Bangpoo Industrial Waste Management Centre
Period: November, 2007 – March, 2008
Details of service: Consulting service for initial operations of the incineration system. -
Srisaket Water Treatment PlantCustomer: Provincial Waterworks Authority of Thailand (PWA)
Period: May, 2007- May, 2009
Details of Service: O&M for Water Treatment Facilities to supply water to PWA’s customers in Srisaket area. -
Water Reclamation SystemCustomer: N/A
Period: 2017 – 2019
Details of Service: EPC for 1st Phase (7,500 m3/day) and 2nd Phase (2,500 m3/day) -
9 MW CFB Incineration Power Plant (Sakeo)Customer: Green Power Energy Co., Ltd.
Period: March 2019 – April 2019
Details of Service: Consultation & O&M Supervision for 9 MW CFB Incineration Power Plant in Sakeo